New Acute Hospital at Kai Tak Development Area

Shing Cheong Road,Kai Tak Development Area
Courtesy of Hospital Authority

The New Acute Hospital (NAH) will be one of the largest hospitals in Hong Kong with 2,400 beds, 37 operating theatres and a broad range of clinical services and facilities. The NAH is a designated trauma centre providing 24-hour Accident and Emergency unit, staffed and equipped to handle urgent cases, emergency conditions and major incidents.  

 

The hospital layout is designed for functional efficiency and the convenience of patients and visitors. A multi-level atrium in the Acute Block is the central “hub” of the hospital. It houses admission, centralised waiting areas, and patient and visitor amenities. All buildings are connected by subways, multi-level bridges and landscaped decks. These also link the hospital to the local community and the waterfront promenade. Daylight and natural surroundings benefit the healing process and ease the stress of a hospital environment; many treatment rooms and waiting areas are daylight-illuminated. Landscaping, planted terraces and rehabilitation gardens feature are provided throughout the hospital.

Highlights on Current Status

Site A: Main Works; Site B: Main Works

Project Current Status

Under Construction

No. of MiC

Site A: TBC; Site B: 370

MiC CFA (m²)

Site A: TBC; Site B: 5,773

CFA (m²)

Site A: 416,817; Site B: 156,778

Total Storeys

Site A: 20-21; Site B: 12

MiC Storey

Site A: TBC; Site B: 6

Construction Cycle of Typical MiC Floor (@ Day Cycle

TBC

Construction Commencement Date (Main Works)

Site A: Q2 2023; Site B: Q1 2022

Anticipated Year of Completion

Site A: 2026; Site B: 2025

Structure

Steel

Main Contract Commencement (Site B)

Q1 2022

Main Contract Commencement (Site A)

Q2 2023

Manufacture of MiC Modules (Site B)

Q4 2022

Installation of MiC Modules (Site B)

Q3 2023

Anticipated Date of Completion (Site B)

2025

Anticipated Date of Completion (Site A)

2026

Last Updated: 04.01.2024 13:50:23

Adopting MiC to Build Light Public Housing (LPH) to Expedite Housing Supply

The Policy Address 2022 announced the construction of LPH. The LPH Scheme is led by the Architectural Services Department with the adoption of MiC. The Housing Bureau has selected eight sites in Tuen Mun, Yuen Long, Ma On Shan, Kai Tak, Ngau Tau Kok and Chai Wai, providing around 30,000 LPH units. The construction period takes only one to two years. Each units equipped with self-contained toilet and basic facilities such as water heater and air-con. The first batch of around 2,100 units will be completed in 2024-25 and the remaining units will be completed by phases in 2025-26 and 2026-27, so as to shorten the waiting time of public housing.