Quarantine Camp in Lei Yue Mun

Lei Yue Mun Park and Holiday Village, Chai Wan
Courtesy of CSHK

Lei Yue Mun Quarantine Camp is a project constructed in response to the COVID-2019. It is an emergency Design & Build project. Under the efforts of different parties, the isolation camp designed and constructed two isolation zones to provide a total of 352 wards to the Department of Health. MiC was adopted to speed up the construction time in order to provide a quick response in meeting the arising demands of the pandemic. 

Courtesy of CSHK

Highlights on Current Status

Completed in Apr 2020

Project Current Status

Completed

No. of MiC Modules

Site A: 118; Site B: 234

CFA (m²)

Site A: 2,052; Site B: 6,077

Project Period (days)

Site A: 25; Site B: 55

Total Storeys

Site A: 1; Site B: 1-2

MiC Storeys

Site A:1; Site B:1-2

Date of Construction Commencement

Feb 2020

Date of Completion

Apr 2020

Structure

Steel

Site A & Site B Construction Commencement Date

Feb 2020

Site A Completion

Feb 2020

Site B Completion

Apr 2020

    The information contained in this page has been authorised being uploaded.

     

    Disclaimer

    The CIC does not warrant or guarantee the accuracy and suitability of the information contained in this page in any particular case. The CIC disclaims all liabilities for any loss or damage to any person arising from or as a consequence of the use of or reliance on any information contained in or omitted from this page.

Last Updated: 03.02.2023 17:36:50

Adopting MiC to Build Light Public Housing (LPH) to Expedite Housing Supply

The Policy Address 2022 announced the construction of LPH. The LPH Scheme is led by the Architectural Services Department with the adoption of MiC. The Housing Bureau has selected eight sites in Tuen Mun, Yuen Long, Ma On Shan, Kai Tak, Ngau Tau Kok and Chai Wai, providing around 30,000 LPH units. The construction period takes only one to two years. Each units equipped with self-contained toilet and basic facilities such as water heater and air-con. The first batch of around 2,100 units will be completed in 2024-25 and the remaining units will be completed by phases in 2025-26 and 2026-27, so as to shorten the waiting time of public housing.

HOT TOPIC