Courtesy of CSHK
Lei Yue Mun Quarantine Camp is a project constructed in response to the COVID-2019. It is an emergency Design & Build project. Under the efforts of different parties, the isolation camp designed and constructed two isolation zones to provide a total of 352 wards to the Department of Health. MiC was adopted to speed up the construction time in order to provide a quick response in meeting the arising demands of the pandemic.
Main Contractor
Structural Engineer
Building Service Engineer
Courtesy of CSHK
Highlights on Current Status
Completed in Apr 2020
Project Current Status
Completed
No. of MiC Modules
Site A: 118; Site B: 234
CFA (m²)
Site A: 2,052; Site B: 6,077
Project Period (days)
Site A: 25; Site B: 55
Total Storeys
Site A: 1; Site B: 1-2
MiC Storeys
Site A:1; Site B:1-2
Date of Construction Commencement
Feb 2020
Date of Completion
Apr 2020
Structure
Steel
Last Updated: 03.02.2023 17:36:50