InnoCell

Science Park, Pak Shek Kok, Tai Po
Courtesy of HKSTP

Located in Hong Kong Science Park, InnoCell is a pilot project of using Modular Integrated Construction (MiC) in Hong Kong. It provides a minimum of 500 bedspaces. Room types include Standard Studio, Sleepbox, Co-living and Family Unit (Recreational and co-living and co-working space integrated with the residential units) with supporting ancillary facilities. It is a smart living and co-creation community for tech talents after the completion of project.

The 17-storey building sits on a 32,000-sq ft. site adjacent to the southeast entrance of Hong Kong Science Park.The building is assembled by 418 modules and provides 5 types of room.

InnoCell gained global recognition by being Highly Commended in the Experimental - Future Project category, in the 2020/2021 World Architecture Festival Awards (WAF). For details, please visit World Architecture Festival Website. 

HKSTP formally launched the InnoCell on 7 April 2021.

 

 

Related News:

07/04/2021   HKSTP

HKSTP LAUNCHES INNOCELL – A SMART LIVING AND CO-CREATION SPACE PURPOSE-BUILT FOR I&T TALENT TO FOSTER HONG KONG’S GROWING INNOVATION COMMUNITY

 

20/05/2022   WSP

InnoCell Wins HKIE Structural Excellence Award 2022

 

 

 

MiC Journey for InnoCell Courtesy of HKSTP

Highlights on Current Status

Completed in October 2020

Project Current Status

Completed

No. of MiC Modules

418

CFA (m²)

19,000

MiC CFA (m²)

10,990

Superstructure Storeys

17

MiC Storeys

15

Construction Cycle of Typical MiC Floor (@ Day Cycle)

3 Days

Construction Commencement Date

Dec 2018

Year of Completion

Q4 2020

Structure

Hybrid

Public Annoucement Date on Use of MiC

May 2018

Construction Commencement Date

Dec 2018

Modules Manufacturing Date

Oct 2019

Module Installation Commencement Date

Jan 2020

Date of Completion

Q4 2020

Module Type Description L (mm) W (mm) H (mm) Internal floor area (m2) Weight (Tons) per module Qty

CO

Coliving

5410

3100

3050

23

Approx. 22

120

ST

Standard Studio

7350

3100

3050

23

Approx. 22

206

SS

Sleepbox Studio

7350

3100

3050

23

Approx. 22

39

FA

Family Unit (Paired Modules)

7350

3100

3050

23

Approx. 22

52

0

Others

7350

3100

3050

23

Approx. 22

1

 

 

 

 

 

 

Total

418

Learn more about the project

WSP (HK) Limited, the Structural Engineering Consultant of the InnoCell Project, has won a merit award in the Hong Kong Institution of Engineers (HKIE) Innovation Awards 2020 (Category I – An Invention) for their Innovative MiC Design Approach for InnoCell.

Due to the innovation and environmental sustainability in architecture and design, InnoCell has received Rethinking The Future Awards 2020 - Second Award. The project stands out among 1,500+ entries. Click here for more information about the award.

By leveraging the Building Information Modelling (BIM) technology in this project, the project team - Hong Kong Science & Technology Parks Corporation, Hip Hing Engineering Company Limited, and Leigh & Orange Limited, has won the Autodesk Hong Kong BIM Awards 2020. For their video, please click here.

    The information contained in this page has been authorised being uploaded.

     

    Disclaimer

    The CIC does not warrant or guarantee the accuracy and suitability of the information contained in this page in any particular case. The CIC disclaims all liabilities for any loss or damage to any person arising from or as a consequence of the use of or reliance on any information contained in or omitted from this page.

Last Updated: 24.07.2023 13:56:49

Adopting MiC to Build Light Public Housing (LPH) to Expedite Housing Supply

The Policy Address 2022 announced the construction of LPH. The LPH Scheme is led by the Architectural Services Department with the adoption of MiC. The Housing Bureau has selected eight sites in Tuen Mun, Yuen Long, Ma On Shan, Kai Tak, Ngau Tau Kok and Chai Wai, providing around 30,000 LPH units. The construction period takes only one to two years. Each units equipped with self-contained toilet and basic facilities such as water heater and air-con. The first batch of around 2,100 units will be completed in 2024-25 and the remaining units will be completed by phases in 2025-26 and 2026-27, so as to shorten the waiting time of public housing.