Residential Care Homes for the Elderly ("RCHE") in Kwu Tung North

Area 29, Kwu Tung North New Development Area
Courtesy of ArchSD

The Architectural Services Department's ''Multi-welfare Services Complex'' for the Social Welfare Department in Kwu Tung North is an 8-storey building, providing 7 numbers of 250 places residential care homes for the elderly, care and attention home for disabled persons, and day activity centre cum hostel for mentally disabled persons.

The residential care homes for the elderly of the ''Multi-welfare Services Complex'' will provide reprovisioning accommodation for the eligible elderly residents currently living in Dills Corner Garden in the vicinity. The building will be built using Modular Integrated Construction [''MiC''] technology.

 

 

Related News:

29/05/2022   Development Bureau

古洞北福利服務綜合大樓 (Chinese only)

 

25/05/2022   SOCAM

組裝合成建築 邁向綠色社區 (Chinese only)

 

Courtesy of ArchSD

Highlights on Current Status

Works after Installation of MiC Modules

Project Current Status

Design & Construction Stage

No. of MiC Modules

1,764

CFA (m²)

Approx. 43,760

MiC CFA (m²)

Approx.18,350

Superstructure Storeys

8

MiC Storeys

7

Construction Cycle of Typical MiC Floor (@ Day cycle)

15 Days

Construction Commencement Date

Dec 2019

Target Year of Completion

Q4 2022

Structure

Concrete

Construction Commencement Date

Dec 2019

Commencement of MiC Works

Q1 2021

Completion Date of MiC Installation

Q1 2022

Anticipated Date of Completion

Q4 2022

Module Type No. Module Type (Steel/ Concrete) Width (mm) Length (mm) Length (mm) Inlcuding Corrider & AC Platform Height (mm) Weight (tonnes) No.
MiC-1/1a Concrete  2,560   3,850   3,850   3,300   14   294 
MiC-2/2a Concrete  2,560   3,240   3,240   3,450   16   294 
MiC-3/3a Concrete  1,370   6,000   6,000   3,300   12   294 
MiC-4/4a Concrete  2,200   6,000   6,000   3,300   16   294 
MiC-5/5a Concrete  2,200   6,000   6,000   3,300   16   294 
MiC-6/6a Concrete  2,500   6,000   6,000   3,300   16   294 
            Total  1,764 

    The information contained in this page has been authorised being uploaded.

     

    Disclaimer

    The CIC does not warrant or guarantee the accuracy and suitability of the information contained in this page in any particular case. The CIC disclaims all liabilities for any loss or damage to any person arising from or as a consequence of the use of or reliance on any information contained in or omitted from this page.

Last Updated: 06.06.2022 15:01:14

The Chief Executive's 2022 Policy Address

To foster the development of MiC

The Chief Executive delivered the 2022 Policy Address on 19 October. To enhance Quantity, Speed, Efficiency and Quality, the Government will increase public housing and land supply by different measures, including the building of Light Public Housing by MiC to shorten the waiting time of public housing. The Housing Authority and Housing Society will adopt the MiC in more public housing projects. The DEVB will establish a cross-departmental steering committee, to streamline approval processes, and also making available land in the Northern Metropolis for manufacturing and storage of modules.

HOT TOPIC