Public Housing Development at Tak Tin Street

Lam Tin

The project is located in Lam Tin (North). There is one 33-storey domestic block sitting on a 5-storey podium, providing 495 flats to be constructed in MiC. 

Highlights on Current Status

Manufacture of MiC Modules

Project Current Status

Under Construction

No. of MiC Modules

1,023

CFA (m²)

22,341

MiC GFA (m²)

8,904

Total Storeys

38

MiC Storeys

33

Construction Cycle of Typical MiC Floor (@ Day Cycle)

6

Construction Commencement Date

Q2 2023

Anticipated Year of Completion

2027

Structure

Concrete

Design Consultancy Commencement

Q4 2020

Foundation Works

Q2 2023 - Q3 2024

Main Contract

Q3 2024 - Q1 2027

Date of Module Installation

Q2 2025 - Q1 2026

Anticipated Completion Date

2027

Module Type Module System W (mm) L (mm) L (mm) Inlcuding Corrider & AC Platform H (mm) Weight (Tons) per module Qty
MiC No.1 Concrete                           1,950                    3,590  -                     2,815                           31                                          66
MiC No.1R Concrete                           1,950                    3,590  -                     2,815                           31                                        132
MiC No.2 Concrete                           2,485  -                     5,050                    2,815                           24                                          66
MiC No.2R Concrete                           2,485  -                     5,050                    2,815                           24                                        132
MiC No.1A Concrete                           1,950  -                     4,190                    2,815                           31                                        132
MiC No.1AR Concrete                           1,950  -                     4,190                    2,815                           31                                        165
MiC No.2A Concrete                           2,485                    4,945  -                     2,815                           25                                        132
MiC No.2AR Concrete                           2,485                    4,945  -                     2,815                           25                                        165
MiC EMR Concrete                           1,490                    3,865  -                     2,815                           11                                          33
            Total 1,023
Last Updated: 08.01.2026 15:40:28

Adopting MiC to Build Light Public Housing (LPH) to Expedite Housing Supply

The Policy Address 2022 announced the construction of LPH. The LPH Scheme is led by the Architectural Services Department with the adoption of MiC. The Housing Bureau has selected eight sites in Tuen Mun, Yuen Long, Ma On Shan, Kai Tak, Ngau Tau Kok and Chai Wai, providing around 30,000 LPH units. The construction period takes only one to two years. Each units equipped with self-contained toilet and basic facilities such as water heater and air-con. The first batch of around 2,100 units will be completed in 2024-25 and the remaining units will be completed by phases in 2025-26 and 2026-27, so as to shorten the waiting time of public housing.