Construction of Public Housing Development at Fanling North Area 15 East Phase 1

Fanling North Area

The project is located in Fanling North Area. There are three domestic blocks and one of the block with 40 domestic storeys (Phase 1A - Block 2) will be constructed in MiC.

Highlights on Current Status

Foundation Works Completed

Project Current Status

Under Construction

No. of MiC Modules

3,000

CFA (m²)

33,551

MiC CFA (m²)

TBA

Construction Cycle of Typical MiC Floor (@Day Cycle)

4 - 6

Total Storeys

40

MiC Storeys

40

Construction Commencement Date

Q2 2022

Anticipated Year of Completion

TBA

Structure

Concrete

Foundation Works

Q2 2022

Main Contract

Q3 2023 - Q2 2026

Manufacture of MiC Modules Commenced

Q2 2024

Installation of MiC Modules Commenced

Q3 2024

    The information contained in this page has been authorised being uploaded.

     

    Disclaimer

    The CIC does not warrant or guarantee the accuracy and suitability of the information contained in this page in any particular case.  The CIC disclaims all liabilities for any loss or damage to any person arising from or as a consequence of the use of or reliance on any information contained in or omitted from this page.

Last Updated: 24.05.2024 15:17:31

Adopting MiC to Build Light Public Housing (LPH) to Expedite Housing Supply

The Policy Address 2022 announced the construction of LPH. The LPH Scheme is led by the Architectural Services Department with the adoption of MiC. The Housing Bureau has selected eight sites in Tuen Mun, Yuen Long, Ma On Shan, Kai Tak, Ngau Tau Kok and Chai Wai, providing around 30,000 LPH units. The construction period takes only one to two years. Each units equipped with self-contained toilet and basic facilities such as water heater and air-con. The first batch of around 2,100 units will be completed in 2024-25 and the remaining units will be completed by phases in 2025-26 and 2026-27, so as to shorten the waiting time of public housing.

HOT TOPIC