Construction of Public Housing Development at Fanling North Area 15 East Phase 1

Fanling North Area

The project is located in Fanling North Area. There are three domestic blocks and one of the block with 40 domestic storeys (Phase 1A - Block 2) will be constructed in MiC.

Highlights on Current Status

Foundation Works Completed

Project Current Status

Under Construction

No. of MiC Modules

3,000

CFA (m²)

33,551

MiC CFA (m²)

TBA

Construction Cycle of Typical MiC Floor (@Day Cycle)

4 - 6

Total Storeys

40

MiC Storeys

40

Construction Commencement Date

Q2 2022

Anticipated Year of Completion

TBA

Structure

Concrete

Foundation Works

Q2 2022

Main Contract

Q3 2023 - Q2 2026

Manufacture of MiC Modules Commenced

Q2 2024

Installation of MiC Modules Commenced

Q3 2024

    The information contained in this page has been authorised being uploaded.

     

    Disclaimer

    The CIC does not warrant or guarantee the accuracy and suitability of the information contained in this page in any particular case.  The CIC disclaims all liabilities for any loss or damage to any person arising from or as a consequence of the use of or reliance on any information contained in or omitted from this page.

Last Updated: 24.05.2024 15:17:31

About MiMEP

Multi-trade Integrated Mechanical, Electrical and Plumbing (MiMEP) is the integration of multi-trade building services components, into a single volumetric assembly of prefabricated modules, manufactured off-site in a workshop, then transported to the site for connection of modules to complete various trades of building services installations to minimise on-site works. MiMEP can integrate with structural element, architectural builders’ works and finishes (ABWF) to form an advanced assembly, such as false ceiling unit and plant room unit to enhance the productivity.