Construction of Public Housing Development at Kwu Tung North Area 19 Phase 1A and Phase 1B

Kwu Tung North Area 19
Kwu Tung North Area 19 Phase 1

The project is located in Kwu Tung North Area 19 Phase 1A and Phase 1B. There are six 38-40 storey domestic blocks with 4,968 flats by MiC. 

Highlights on Current Status

Superstructure Works

Project Current Status

Under Construction

No. of MiC Modules

12,950

CFA (m²)

220,924

MiC CFA (m²)

135,727

Construction Cycle of Typical MiC Floor (@Day Cycle)

4

Total Storeys

38 - 40

MiC Storeys

Block 1: 40; Blocks 2 - 5: 39; Block 6: 38

Construction Commencement Date

Phase 1A: Q2 2022; Phase 1B: Q3 2023

Date of Completion

TBA

Structure

Concrete

Foundation Works (Phase 1A)

Q2 2022 - Q3 2023

Foundation Works (Phase 1B)

Q2 2023 - Q1 2024

Main Contract Commenced

Q3 2023

The information contained in this page has been authorised being uploaded.

 

Disclaimer

The CIC does not warrant or guarantee the accuracy and suitability of the information contained in this page in any particular case.  The CIC disclaims all liabilities for any loss or damage to any person arising from or as a consequence of the use of or reliance on any information contained in or omitted from this page

Last Updated: 24.05.2024 15:21:05

Adopting MiC to Build Light Public Housing (LPH) to Expedite Housing Supply

The Policy Address 2022 announced the construction of LPH. The LPH Scheme is led by the Architectural Services Department with the adoption of MiC. The Housing Bureau has selected eight sites in Tuen Mun, Yuen Long, Ma On Shan, Kai Tak, Ngau Tau Kok and Chai Wai, providing around 30,000 LPH units. The construction period takes only one to two years. Each units equipped with self-contained toilet and basic facilities such as water heater and air-con. The first batch of around 2,100 units will be completed in 2024-25 and the remaining units will be completed by phases in 2025-26 and 2026-27, so as to shorten the waiting time of public housing.

HOT TOPIC