Relocation of ShaTin Sewage Treatment Caverns Project - Community Liaison Centre

Mui Tsz Lam Road, Ma On Shan, Shatin
Courtesy of DSD

The construction of Community Liaison Centre adopts MiC and integrated with BIM technology. It is a one storey centre which consists of 14 modules.  The centre promotes the "Relocation of Sha Tin Sewage Treatment Works to Caverns" Project and facilitates the communication with the public as to better serve the society by providing a co-working space for organisations.

 

Related News:

15/10/2021  Drainage Sevices Department

Relocation of Sha Tin Sewage Treatment Works to Caverns was awarded the ICE Annual Awards 2021 Edmund Hambly Medal Winner

Courtesy of AECOM

Highlights on Current Status

Completed

Project Current Status

Completed

No. of MiC Modules

14

CFA (m²)

250

MiC CFA (m²)

250

Superstructure Storeys

1

MiC Storeys

1

Construction Commencement Date

Aug 2019

Year of Completion

Jul 2020

Structure

Steel

Construction Commencement Date

Aug 2019

Completion of Module Installation

May 2020

Year of Completion

Jul 2020

Learn more about the project

The Drainage Services Department adopts a number of innovative measures in the project  of “Relocation of Sha Tin Sewage Treatment Works to Caverns”, including the use of MiC to build a community liaison center, the use of Design for Manufacture and Assembly to construct temporary bridge. The project also uses BIM and digital management, and promotes renewable energy, implements carbon and waste reduction measures. In addition to efficiency, it can also reduce nuisance to the public. Above all, the project won the Construction Industry Council Sustainable Construction Award 2020.

    The information contained in this page has been authorised being uploaded.

     

    Disclaimer

    The CIC does not warrant or guarantee the accuracy and suitability of the information contained in this page in any particular case. The CIC disclaims all liabilities for any loss or damage to any person arising from or as a consequence of the use of or reliance on any information contained in or omitted from this page.

Last Updated: 28.10.2021 10:42:34

New Isolation Facilities in Hong Kong

Alleviate demand pressure for isolation by MiC and DfMA

In view of the 5th wave of the COVID-19, new isolation facilities and Pop-up Community Vaccination Centres were built by MiC and DfMA with full speed. Eight Community Isolation Facilities projects from China State Construction International providing over 50,000 isolation beds. Supported by the Central Government, the Lok Ma Chau Loop Hospital for Emergency was completed in April 2022. Meanwhile, two MiC transitional housing projects were used as community isolation facilities, providing more than 2,500 units.