Public Housing Developments at Anderson Road Quarry Sites R2-6 and R2-7

Anderson Road Quarry Site
Courtesy of Hong Kong Housing Authority

The project is located in Anderson Road Quarry Site Area. There are two 30-storeydomestic blocks with 990 flats by Modular Integrated Construction (MiC) at Site R2-6; andone 18-storey domestic block with 420 flats by MiC at Site R2-7.

Highlights on Current Status

Module Installation

Project Current Status

Under Construction

No. of MiC Modules

4,065

CFA (m²)

TBA

MiC CFA (m²)

R2-6: 58,570; R2-7 Domestic Block: 23,531

Total Storeys

R2-6: 30; R2-7: 18

MiC Storeys

R2-6: 28; R2-7: 17

Construction Cycle of Typical MiC Floor (@ Day Cycle)

TBA

Construction Commencement Date

31 Dec 2021

Anticipated Year of Completion

R2-6: Q1 2025; R2-7: Q3 2024

Structure

Concrete

Foundation Works Commencement

Dec 2021

Main Contract Commencement

Oct 2022

Manufacture of MiC Modules Commencement

Q2 2023

Installation of MiC Modules Commencement

Q3 2023

    The information contained in this page has been authorised being uploaded.

     

    Disclaimer

    The CIC does not warrant or guarantee the accuracy and suitability of the information contained in this page in any particular case.  The CIC disclaims all liabilities for any loss or damage to any person arising from or as a consequence of the use of or reliance on any information contained in or omitted from this page

Last Updated: 16.04.2024 16:51:29

Adopting MiC to Build Light Public Housing (LPH) to Expedite Housing Supply

The Policy Address 2022 announced the construction of LPH. The LPH Scheme is led by the Architectural Services Department with the adoption of MiC. The Housing Bureau has selected eight sites in Tuen Mun, Yuen Long, Ma On Shan, Kai Tak, Ngau Tau Kok and Chai Wai, providing around 30,000 LPH units. The construction period takes only one to two years. Each units equipped with self-contained toilet and basic facilities such as water heater and air-con. The first batch of around 2,100 units will be completed in 2024-25 and the remaining units will be completed by phases in 2025-26 and 2026-27, so as to shorten the waiting time of public housing.