Courtesy of Hong Kong Housing Authority
The project is located in Anderson Road Quarry Site Area. There are two 30-storeydomestic blocks with 990 flats by Modular Integrated Construction (MiC) at Site R2-6; andone 18-storey domestic block with 420 flats by MiC at Site R2-7.
Client
Main Contractor
Structural Engineer
Building Services Engineer
Quantity Surveyor
Traffic Engineer
Highlights on Current Status
Post Module Installation Works
Project Current Status
Under Construction
No. of MiC Modules
4,065
CFA (m²)
TBA
MiC CFA (m²)
R2-6: 58,570; R2-7 Domestic Block: 23,531
Total Storeys
R2-6: 30; R2-7: 18
MiC Storeys
R2-6: 28; R2-7: 17
Construction Cycle of Typical MiC Floor (@ Day Cycle)
TBA
Construction Commencement Date
31 Dec 2021
Anticipated Year of Completion
2025
Structure
Concrete
Last Updated: 23.12.2024 11:36:30
Adopting MiC to Build Light Public Housing (LPH) to Expedite Housing Supply
HOT TOPIC