Construction of a 36-Classroom Primary School at Area 9, Tai Po

Tai Po

Scheduled for completion in 2023, the 36-classroom primary school at Tai Po Area 9 is the first primary school building in Hong Kong adopting MiC for all 36 numbers of typical classrooms, typical lavatories for students, typical electrical rooms and pantry. The valuable experience of MiC design and implementation gained in this project will set a good example and lesson learnt for the forthcoming MiC school developments in the future.

 

The repetitive design of all 36 standardised classrooms is well-suited for the adoption of MiC. In general, each classroom is sub-divided into four volumetric units prefabricated with reinforced concrete elements and completed with the required finishes, fixtures and building services in an off-site factory under stringent quality control. In addition, MiC is also adopted for the typical lavatories for student, typical electrical rooms and pantry. The total number of MiC modules to be constructed for the school is 181. 

Highlights on Current Status

Works after Module Installation

Project Current Status

Under Construction

No. of MiC Modules

181

CFA (m²)

13,233

MiC CFA (m²)

3,285

Total Storeys

7

MiC Storeys

6

Construction Cycle of Typical MiC Floor (@ Day Cycle)

6

Construction Commencement Date

May 2021

Date of Completion

2023

Structure

Concrete

Main Contract Works Commencement

May 2021

Foundation Works Commencement

Aug 2021

Manufacture of MiC Modules Commencement

Mar 2022

Installation of MiC Modules Commencement

Dec 2022

Date of Completion

2023

    The information contained in this page has been authorised being uploaded.

     

    Disclaimer

    The CIC does not warrant or guarantee the accuracy and suitability of the information contained in this page in any particular case. The CIC disclaims all liabilities for any loss or damage to any person arising from or as a consequence of the use of or reliance on any information contained in or omitted from this page.

Last Updated: 15.01.2024 14:25:05

Adopting MiC to Build Light Public Housing (LPH) to Expedite Housing Supply

The Policy Address 2022 announced the construction of LPH. The LPH Scheme is led by the Architectural Services Department with the adoption of MiC. The Housing Bureau has selected eight sites in Tuen Mun, Yuen Long, Ma On Shan, Kai Tak, Ngau Tau Kok and Chai Wai, providing around 30,000 LPH units. The construction period takes only one to two years. Each units equipped with self-contained toilet and basic facilities such as water heater and air-con. The first batch of around 2,100 units will be completed in 2024-25 and the remaining units will be completed by phases in 2025-26 and 2026-27, so as to shorten the waiting time of public housing.

HOT TOPIC