The construction work for the 5th phase of the Student Hostel project at City University of Hong Kong (CityU) at Whitehead, Ma On Shan officially commenced in January 2022. In addition to hostel rooms, there will be communal area, corridors, toilets and plant rooms adopted MiC technology, with more than 1,300 MiC modules in the six building blocks. The project is expected to be completed in the second quarter of 2026 and will provide more than 2,000 bed-spaces for CityU undergraduate and postgraduate students.
Related News:
14/02/2022 Gammon Construction
Gammon Construction wins the largest MiC student hostel project in Hong Kong
14/03/2022 City University of Hong Kong
CityU’s Student Hostel at Whitehead promises high-quality academic park
19/12/2022 City University of Hong Kong
18/4/2023 City University of Hong Kong
Visit to CityU Whitehead Student Hostel project site by DevB and ArchSD
6/7/2023 Construction Industry Council
Client
Main Contractor
MiC Supplier
Structural Engineer
Building Services Engineer
Quantity Surveyor
Traffic Consultant
Highlights on Current Status
Commenced operations in September 2024
Project Current Status
Completed
No. of MiC Modules
1,344
CFA (m²)
Approx. 48,000
MiC CFA (m²)
Approx. 26,000
Superstructure Storeys
13-17
MiC Storeys
13-17
Construction Cycle of Typical MiC Floor (@ Day Cycle)
4 Days
Construction Commencement Date
Q1 2022
Main Contract Completion
Dec 2023
Structure
Steel
Module Type | Module System | Width (mm) | Length (mm) | Length (mm) Inlcuding Corrider & AC Platform | Height (mm) | Weight (tonnes) | No. |
---|---|---|---|---|---|---|---|
Type 1A | Steel | 2,665 | 9,000 | 10,000 | 3,105 | 15 | 66 |
Type 3 | Steel | 2,133 | 9,000 | 9,000 | 3,105 | 15 | 33 |
Type 2A | Steel | 3,090 | 7,226 | 7,726 | 3,105 | 18 | 98 |
Type 4 | Steel | 2,000 | 9,416 | 10,416 | 3,105 | 18 | 56 |
Type 5 | Steel | 3,000 | 6,682 | 7,182 | 3,105 | 15 | 889 |
Others | Steel | varies | varies | varies | 3,105 | varies | 202 |
Total: | 1,344 |