The City University of Hong Kong Student Hostel at Whitehead

Whitehead, Ma On Shan
Courtesy of City University of Hong Kong

The construction work for the 5th phase of the Student Hostel project at City University of Hong Kong (CityU) at Whitehead, Ma On Shan officially commenced in January 2022.  In addition to hostel rooms, there will be communal area, corridors, toilets and plant rooms adopted MiC technology, with more than 1,300 MiC modules in the six building blocks. The project is expected to be completed in the second quarter of 2026 and will provide more than 2,000 bed-spaces for CityU undergraduate and postgraduate students.

 

Related News:

14/02/2022      Gammon Construction

Gammon Construction wins the largest MiC student hostel project in Hong Kong

 

14/03/2022      City University of Hong Kong

CityU’s Student Hostel at Whitehead promises high-quality academic park

 

19/12/2022    City University of Hong Kong

New CityU student hostel set to enrich student experience, promoting diversity; innovative technologies reduce construction period

 

18/4/2023      City University of Hong Kong

Visit to CityU Whitehead Student Hostel project site by DevB and ArchSD

 

6/7/2023       Construction Industry Council 

Concerted Efforts from the Construction Industry and Education Sector to Establish a New Chapter for MiC Application

Introduction Video: 馬鞍山學生宿舍項目動土 郭位校長:城大重要里程碑 Courtesy of CityU

Highlights on Current Status

Works after Module Installation

Project Current Status

Under Construction

No. of MiC Modules

1,344

CFA (m²)

Approx. 48,000

MiC CFA (m²)

Approx. 26,000

Superstructure Storeys

13-17

MiC Storeys

13-17

Construction Cycle of Typical MiC Floor (@ Day Cycle)

4 Days

Construction Commencement Date

Q1 2022

Target Main Contract Completion

Dec 2023

Structure

Steel

Construction Commencement Date

Q1 2022

Manufacture of MiC Modules

Sep 2022 - May 2023

Module Installation

Dec 2022 - Jul 2023

Target Main Contract Completion

Dec 2023

Module Type Module System Width (mm) Length (mm) Length (mm) Inlcuding Corrider & AC Platform Height (mm) Weight (tonnes) No.
Type 1A  Steel 2,665 9,000 10,000 3,105 15 66
Type 3 Steel 2,133 9,000 9,000 3,105 15 33
Type 2A Steel 3,090 7,226 7,726 3,105 18 98
Type 4 Steel 2,000 9,416 10,416 3,105 18 56
Type 5 Steel 3,000 6,682 7,182 3,105 15 889
Others  Steel varies varies varies 3,105 varies 202
  Total: 1,344

    The information contained in this page has been authorised being uploaded.

     

    Disclaimer

    The CIC does not warrant or guarantee the accuracy and suitability of the information contained in this page in any particular case. The CIC disclaims all liabilities for any loss or damage to any person arising from or as a consequence of the use of or reliance on any information contained in or omitted from this page.

Last Updated: 11.09.2023 14:38:16

Adopting MiC to Build Light Public Housing (LPH) to Expedite Housing Supply

The Policy Address 2022 announced the construction of LPH. The LPH Scheme is led by the Architectural Services Department with the adoption of MiC. The Housing Bureau has selected eight sites in Tuen Mun, Yuen Long, Ma On Shan, Kai Tak, Ngau Tau Kok and Chai Wai, providing around 30,000 LPH units. The construction period takes only one to two years. Each units equipped with self-contained toilet and basic facilities such as water heater and air-con. The first batch of around 2,100 units will be completed in 2024-25 and the remaining units will be completed by phases in 2025-26 and 2026-27, so as to shorten the waiting time of public housing.