Public Housing Development at Tung Chung Area 99

Tung Chung
Courtesy of Housing Authority

The project is located in Tung Chung Extension Area. There are five domestic blocks and one of the block with 12 domestic storeys (Block 5) will be constructed in MiC. This is the first public housing project in Hong Kong built with MiC method. It is hoped that through this precedent, MiC technology can be extended the adoption to more residential categories, so as to speed up the housing supply and alleviate the housing problems in Hong Kong. 

Courtesy of Housing Authority

Highlights on Current Status

Superstructure Works

Project Current Status

Under Construction

No.of MiC Modules

504

CFA (m²)

8,283

MiC CFA (m²)

5,487

Superstructure Storeys

12

MiC Storeys

12

Construction Cycle of Typical MiC Floor (@ Day Cycle)

6

Construction Commencement Date

3 Mar 2020

Completion Date

TBA

Structure

Concrete

Design Consultancy Commencement

Dec 2019

Foundation Works

Mar 2020 - Mar 2023

    The information contained in this page has been authorised being uploaded.

     

    Disclaimer

    The CIC does not warrant or guarantee the accuracy and suitability of the information contained in this page in any particular case.  The CIC disclaims all liabilities for any loss or damage to any person arising from or as a consequence of the use of or reliance on any information contained in or omitted from this page

Last Updated: 16.04.2024 10:43:52

Adopting MiC to Build Light Public Housing (LPH) to Expedite Housing Supply

The Policy Address 2022 announced the construction of LPH. The LPH Scheme is led by the Architectural Services Department with the adoption of MiC. The Housing Bureau has selected eight sites in Tuen Mun, Yuen Long, Ma On Shan, Kai Tak, Ngau Tau Kok and Chai Wai, providing around 30,000 LPH units. The construction period takes only one to two years. Each units equipped with self-contained toilet and basic facilities such as water heater and air-con. The first batch of around 2,100 units will be completed in 2024-25 and the remaining units will be completed by phases in 2025-26 and 2026-27, so as to shorten the waiting time of public housing.

HOT TOPIC