Nam Cheong Street Modular Social Housing Project ("Nam Cheong 220“)

202 - 220 Nam Cheong Street, Sham Shui Po
Courtesy of HKCSS

Modular Social Housing Projects adopt modular integrated construction to build transitional social housing in idle land. HKCSS aims to provide affordable and transitional social housing to families and persons whom queued for the public rental housing and/ or currently live in dismal and inadequate housing conditions so that their living quality can be improved.

 

Expected to provide totally 89 units. The internal floor area of each unit is between around 10 sqm to 25 sqm. Different module size will be provided for 1-person household unit, 2-person household unit, 3-person household unit and accessible unit.

 

Related News:

19/8/2020  The Hong Kong Council of Social Serevice

(Chinese only)全港首個組合社會房屋竣工 社聯「組合社會房屋計劃」-「南昌220」

 

18/2/2023  new.gov.hk

Housing project moves for reuse

 

2/3/2023  The Hong Kong Council of Social Serevice

「南昌220」組件將在大埔展開「新生」(Chinese only)

 

19/3/2024  Jockey Club Design Institute for Social Innovation

Technical Report on the Deconstruction, Relocation and Reinstallation of MiC Modules in Nam Cheong 220 Transitional Housing Project 

Project timelapse Courtesy of HKCSS

Highlights on Current Status

Tenants Moved In

Project Current Status

Completed

No. of MiC Modules

68

CFA (m²)

2,052

MiC CFA (m²)

2,052

Superstructure Storeys

4

MiC Storeys

4

Construction Cycle of Typical MiC floor ( @ Day cycle)

4 Days

Construction Commencement Date

Aug 2019

Year of Completion

Jul 2020

Structure

Steel

Public Announcement Date on Use of MiC

Jun 2018

Construction Commencement Date

Aug 2019

Modules Manufacturing Commencement Date

Nov 2019

Assembly Commencement Date

Dec 2019

Year of Completion

Jul 2020

Tenant Move in

Aug 2020

Learn more about the project

Watch the interview with the Client and the Members of the Project Team of "Nam Cheong 220"

PLAYLIST

    The information contained in this page has been authorised being uploaded.

     

    Disclaimer

    The CIC does not warrant or guarantee the accuracy and suitability of the information contained in this page in any particular case.  The CIC disclaims all liabilities for any loss or damage to any person arising from or as a consequence of the use of or reliance on any information contained in or omitted from this page.

Last Updated: 19.03.2024 14:15:43

Adopting MiC to Build Light Public Housing (LPH) to Expedite Housing Supply

The Policy Address 2022 announced the construction of LPH. The LPH Scheme is led by the Architectural Services Department with the adoption of MiC. The Housing Bureau has selected eight sites in Tuen Mun, Yuen Long, Ma On Shan, Kai Tak, Ngau Tau Kok and Chai Wai, providing around 30,000 LPH units. The construction period takes only one to two years. Each units equipped with self-contained toilet and basic facilities such as water heater and air-con. The first batch of around 2,100 units will be completed in 2024-25 and the remaining units will be completed by phases in 2025-26 and 2026-27, so as to shorten the waiting time of public housing.