Yen Chow Street Modular Social Housing Project

Junction between Yen Chow Street West and Tung Chau Street, Sham Shui Po
Courtesy of HKCSS

Modular Social Housing - Yen Chow Street Modular Social Housing Project adopt modular integrated construction to build transitional social housing in idle land. HKCSS aims to provide affordable and transitional social housing to families and persons whom queued for the public rental housing and/ or currently live in dismal and inadequate housing conditions so that their living quality can be improved.


HKCSS is  building 2 blocks of 4-storey modular housing and provide around 205 units. The type of modular housing consists of 1-person household unit, 2-person household unit, 3-person household unit and accessible units at the ground floor.

Courtesy of HKCSS

Highlights on Current Status

Manufacture of MiC Modules

Project Current Status

Construction

No. of MiC Modules

TBA

CFA (m²)

6,848

GFA (m²)

5,380

Superstructure Storeys

4

MiC Storeys

4

Construction Cycle of Typical MiC Floor ( @ Day cycle)

TBA

Construction Commencement Date

Nov 2020

Anticipated Year of Completion

Q1 2022

Structure

Concrete

Construction Commencement Date

Nov 2020

Manufacture of MiC Modules Commencement

May 2021

Completion of MiC Modules Installation

Aug 2021

Anticipated Year of Completion

Q1 2022

    The information contained in this page has been authorised being uploaded.

     

    Disclaimer

    The CIC does not warrant or guarantee the accuracy and suitability of the information contained in this page in any particular case. The CIC disclaims all liabilities for any loss or damage to any person arising from or as a consequence of the use of or reliance on any information contained in or omitted from this page.

Last Updated: 10.08.2021 14:21:55

Transitional Housing Projects

In order to relieve the acute shortage of housing, the HKSAR Government announced the three-year transitional housing target of 15,000 units in January 2020. Up to now, two MiC transitional housing projects were completed, including the Nam Cheong 220 by The Hong Kong Council of Social Service and the Junction of Sung Wong Toi Road and To Kwa Wan Road Project by Lok Sin Tong. United Court by Sheng Kung Hui will be commenced shortly. The largest project in Kong Ha Wai by Pok Oi Hospital was commenced in March 2021. Over 6,000 people will be homed by the end of 2022.

Update on the Progress of Supplying Transitional Housing

08.07.2021 Legislative Council of the HKSAR

江夏圍過渡性房屋計劃 - 首批示範單位落地元朗 (Chinese only)

10.06.2021 AluHouse

樂善堂社會房屋計劃「樂屋」 - 宋皇臺道及土瓜灣道交界組合屋項目 (Chinese only)

03.06.2021 Lok Sin Tong

江夏圍過渡性房屋項目正式動土 (Chinese only)

10.05.2021 City's Time

HOT TOPIC