FEHD Sunlight Market

Fu Tung Street near Tung Chung MTR Station

The government had consolidated the area between Fu Tung Street and Cheung Tung Road for building a temporary market in Tung Chung. To expedite the delivery of the project, reference was made to the MiC construction of Skylight Market in Tin Shui Wai which was commissioned in December 2021. As the temporary market is close to the Tung Chung MTR station and the public transport interchange, its convenient location benefits more residents in the area. The temporary market is covered with a canopy, and each stall is equipped with air-conditioning. The 36 stalls are mainly selling fresh provisions such as fish, meat, vegetables and fruits.

Highlight on Current Status

Commissioned in March 2023

Project Current Status

Completed

No. of MiC Module

29

CFA (m²)

1,273

MiC CFA (m²)

446

Total Storeys

1

MiC Storeys

1

Construction Cycle of Typical MiC floor ( @ Day cycle)

N/A

Construction Commencement Date

Q3 2021

Date of Completion

Q4 2022

Structure

Steel

Main Contract Commencement

Q3 2021

Manufacture of MiC Modules

Q4 2021 - Q2 2022

Installation of MiC Modules

Q1 2022 - Q3 2022

Completion

Q4 2022

Module Type  Module System Width (mm) Length (mm) Height (mm) Weight (tonnes) Total Remarks
Customer Service Counter steel frame with concrete slab                           3,000                           5,500                           3,091 8 1  
Stalls Type 1 - Large Stall steel frame with concrete slab                           3,185                           4,985                           3,091 7 12  
Stalls Type 2 - Small Stall steel frame with concrete slab                           2,250                           6,990                           3,066 11.5 12  2 stalls per one container module 
Toilets steel frame with concrete slab                           2,630                           5,415                           3,091 7.5 1  with 3 compartments 
FS Pump Room steel frame with concrete slab                           2,480                           3,375                           2,706 5.5 1  
Water Pump Room & RCP steel frame with concrete slab                           2,980                           9,060                           3,091 12.5 1  
Duty Office steel frame with concrete slab                           2,860                           4,985                           3,091 6.5 1  
           Total  29  

    The information contained in this page has been authorised being uploaded.

     

    Disclaimer

    The CIC does not warrant or guarantee the accuracy and suitability of the information contained in this page in any particular case.  The CIC disclaims all liabilities for any loss or damage to any person arising from or as a consequence of the use of or reliance on any information contained in or omitted from this page.

Last Updated: 06.07.2023 17:05:20

Adopting MiC to Build Light Public Housing (LPH) to Expedite Housing Supply

The Policy Address 2022 announced the construction of LPH. The LPH Scheme is led by the Architectural Services Department with the adoption of MiC. The Housing Bureau has selected eight sites in Tuen Mun, Yuen Long, Ma On Shan, Kai Tak, Ngau Tau Kok and Chai Wai, providing around 30,000 LPH units. The construction period takes only one to two years. Each units equipped with self-contained toilet and basic facilities such as water heater and air-con. The first batch of around 2,100 units will be completed in 2024-25 and the remaining units will be completed by phases in 2025-26 and 2026-27, so as to shorten the waiting time of public housing.