Transitional Housing Project at Ping Che Road, Ta Kwu Ling

Ping Che Road, Ta Kwu Ling (Former Sing Ping School)

This is the second transitional housing project of Pok Oi Hospital built with MiC. The project not only improve the housing problem but also effectively use the Northern Metropolis for housing development. With the activity centre as part of the project, a better community service is provided for residents.

Highlights on Current Status

Foundation Works

Project Current Status

Under Construction

No. of MiC Modules

Approx. 600

GFA (m²)

10,637

MiC GFA (m²)

TBA

Total Storeys

4

MiC Storeys

4

Construction Cycle of Typical MiC Floor (@ Day Cycle)

TBA

Construction Commencement Date

Q4 2022

Anticipated Date of Completion

Q1 2024

Structure

Steel

Construction Commencement Date

Q4 2022

Module Installation Commencement

Q3 2023

Anticipated Date of Completion

Q1 2024

Last Updated: 14.07.2023 16:18:32

Quickly build high-quality Light Public Housing with MiC

The Policy Address 2022 announced the construction of Light Public Housing (LPH)

The LPH Scheme will be led by the Architectural Services Department with the adoption of MiC. The Housing Bureau has selected eight sites in Tuen Mun, Yuen Long, Ma On Shan, Kai Tak, Ngau Tau Kok and Chai Wai, providing around 30,000 LPH units. The construction period takes only one to two years. Each units equipped with self-contained toilet and basic facilities such as water heater and air-con. The first batch of around 2,100 units will be completed in 2024-25 and the remaining units will be completed by phases in 2025-26 and 2026-27, so as to shorten the waiting time of public housing.

HOT TOPIC