Transitional Housing Project at Hung Shui Kiu

Hung Yuen Road near Hung Fuk Estate, Hung Shui Kiu
Courtesy of AluHouse

With technical support by The Urban Renewal Authority, Yan Oi Tong has established its first transitional housing project – Yan Oi House. It aims to provide a better living environment for the grassroots families. Yan Oi House comprises 2 nos. domestic blocks with four storey buildings, providing 410 units.  Each unit is equipped with a bathroom and a cooking area. It takes only a 2-minutes walk to Hung Shui Kiu Light Rail Station. Together with the convenient traffic, It is hoped that Yan Oi House not only provide residents a better living environment but also a better quality of life. 

Highlights on Current Status

Completed in Q2 2023

Project Current Status

Completed

No. of MiC Modules

Approx. 430

GAF (m²)

10,126

Total Storeys

4

MiC Storeys

4

Construction Cycle of Typical MiC Floor (@ Day Cycle)

4

Construction Commencement Date

Q2 2022

Date of Completion

Q2 2023

Structure

Steel

Construction Commencement

Q2 2022

Module Installation

Q1 2023

Date of Completion

Q2 2023

    The information contained in this page has been authorised being uploaded.

     

    Disclaimer

    The CIC does not warrant or guarantee the accuracy and suitability of the information contained in this page in any particular case. The CIC disclaims all liabilities for any loss or damage to any person arising from or as a consequence of the use of or reliance on any information contained in or omitted from this page.

Last Updated: 05.12.2023 10:19:32

Adopting MiC to Build Light Public Housing (LPH) to Expedite Housing Supply

The Policy Address 2022 announced the construction of LPH. The LPH Scheme is led by the Architectural Services Department with the adoption of MiC. The Housing Bureau has selected eight sites in Tuen Mun, Yuen Long, Ma On Shan, Kai Tak, Ngau Tau Kok and Chai Wai, providing around 30,000 LPH units. The construction period takes only one to two years. Each units equipped with self-contained toilet and basic facilities such as water heater and air-con. The first batch of around 2,100 units will be completed in 2024-25 and the remaining units will be completed by phases in 2025-26 and 2026-27, so as to shorten the waiting time of public housing.

HOT TOPIC