Construction of Fire Station-cum-ambulance Depot with Departmental Quarters and Facilities in Area 72, Tseung Kwan O

Area 72, Tseung Kwan O

The Fire Services Department plans to build a 17-storey building with a rooftop in Area 72, Tseung Kwan O, which will be used as a fire station-cum-ambulance depot, and provide 132 departmental quarters (DQ) and other fire services facilities. The scope of the Project includes – i) construction of FSAD with a 5-bay appliance room; ii) reprovisioning of the CEPD store; iii) reprovisioning of the office of FSITF; iv) provision of outdoor parking spaces for FSD operational vehicles and outdoor parking spaces for DQ ; and v)provision of 132  DQ units and related facilities. MiC is adopted for the 12 DQ floors to shorten the construction time.

Highlights on Current Status

Completed

Project Current Status

Completed

No. of MiC Modules

Around 660

CFA (m²)

15,995

MiC CFA (m²)

6,600

Total Storeys

17

MiC Storey

12

Construction Commencement Date

Q2 2022

Anticipated Date of Completion

Q2 2025

Structure

Concrete

Commencement of Main Contract

Q2 2022

Manufacture of MiC Modules

Q4 2023 - Q1 2024

Installation of MiC Modules Completed

Q4 2024

Date of Completion

2025

Last Updated: 08.01.2026 12:02:01

About MiMEP

Multi-trade Integrated Mechanical, Electrical and Plumbing (MiMEP) is the integration of multi-trade building services components, into a single volumetric assembly of prefabricated modules, manufactured off-site in a workshop, then transported to the site for connection of modules to complete various trades of building services installations to minimise on-site works. MiMEP can integrate with structural element, architectural builders’ works and finishes (ABWF) to form an advanced assembly, such as false ceiling unit and plant room unit to enhance the productivity.