Design and Build Contract for Transitional Housing Project at Luen Yan Street, Tsuen Wan

Luen Yan Street, Tsuen Wan

The project building is named as "荃福居",  providing approximately 196 nos. of residential units for estimated 408 nos. of residents. There are 1-4 person units and barrier-free units, each with its own toilet, bathroom and cooking space.

 

There will also be facilities such as community kitchens, green convenience stores and organic gardens to provide hot meals to residents and those in need in the community, and to promote food waste recycling and food waste composting education in a one-stop way.

 

It is hoped that "Tsuen Fook Kui" can provide an appropriate transitional suitable housing for grassroots residents in the Tsuen Wan community with poor living conditions in the future, so as to ease the waiting list for public housing families and other residents.

 

Related News

19/7/2023 CR Construction Company Limited

(Chinese only) We Build系列:「組裝合成」建築法

Client

Structural Engineer

Building Services Engineer

Quantity Surveyor

Traffic Consultant

Highlights on Current Status

Completed in May 2023

Project Current Status

Completed

No. of MiC Modules

193

CFA (m²)

1,932.8

MiC CFA (m²)

1,760.6

Total Storeys

4

MiC Storeys

4

Construction Cycle of Typical MiC Floor (@ Day Cycle)

6

Construction Commencement Date

April 2022

Date of Completion

2023

Structure

Hybrid

Main Contract Commencement

April 2022

Foundation Works Commencement

Jul 2022

Manufacture of MiC Modules Commencement

Sep 2022

Installation of MiC Modules Commencement

Nov 2022

Date of Completion

May 2023

Module Type  Module System Width (mm) Length (mm) Length (mm) Inlcuding Corrider & AC Platform Height (mm) No.
A Steel 2,805 4,200 5,250 3,000 12
B Steel 2,805 4,200 5,250 3,000 161
C Steel 2,805 6,900 7,950 3,000 16
D Steel 2,805 5,000 6,050 3,000 3
E Steel 2,805 5,000 6,050 3,000 1
Total 193

    The information contained in this page has been authorised being uploaded.

     

    Disclaimer

    The CIC does not warrant or guarantee the accuracy and suitability of the information contained in this page in any particular case.  The CIC disclaims all liabilities for any loss or damage to any person arising from or as a consequence of the use of or reliance on any information contained in or omitted from this page

Last Updated: 24.07.2023 14:15:58

Adopting MiC to Build Light Public Housing (LPH) to Expedite Housing Supply

The Policy Address 2022 announced the construction of LPH. The LPH Scheme is led by the Architectural Services Department with the adoption of MiC. The Housing Bureau has selected eight sites in Tuen Mun, Yuen Long, Ma On Shan, Kai Tak, Ngau Tau Kok and Chai Wai, providing around 30,000 LPH units. The construction period takes only one to two years. Each units equipped with self-contained toilet and basic facilities such as water heater and air-con. The first batch of around 2,100 units will be completed in 2024-25 and the remaining units will be completed by phases in 2025-26 and 2026-27, so as to shorten the waiting time of public housing.

HOT TOPIC