Transitional Housing at "Yan Chai Residence" at Hoi Hing Road, Tsuen Wan

Junction of Hoi Hing Road and Hoi Kok Street, Tsuen Wan
Courtesy of Yan Chai Hospital Board

Provision of transitional housing with community support services for individuals or families in Tsuen Wan who are queuing up for public housing, and are currently living in inadequate housing conditions or in urgent need for community support. 

Introduction of "Yan Chai Residence"

Highlights on Current Status

Completed in Q3 2023

Project Current Status

Completed

No. of Units

212

CFA (m²)

5,032

Total Storeys

2

MiC Storeys

2

Construction Commencement Date

Jul 2022

Completion Date

Q3 2023

Structure

Steel

Construction Commencement Date

Jul 2022

Completion Date

Q3 2023

    The information contained in this page has been authorised being uploaded.

     

    Disclaimer

    The CIC does not warrant or guarantee the accuracy and suitability of the information contained in this page in any particular case.  The CIC disclaims all liabilities for any loss or damage to any person arising from or as a consequence of the use of or reliance on any information contained in or omitted from this page

Last Updated: 05.12.2023 09:44:17

Adopting MiC to Build Light Public Housing (LPH) to Expedite Housing Supply

The Policy Address 2022 announced the construction of LPH. The LPH Scheme is led by the Architectural Services Department with the adoption of MiC. The Housing Bureau has selected eight sites in Tuen Mun, Yuen Long, Ma On Shan, Kai Tak, Ngau Tau Kok and Chai Wai, providing around 30,000 LPH units. The construction period takes only one to two years. Each units equipped with self-contained toilet and basic facilities such as water heater and air-con. The first batch of around 2,100 units will be completed in 2024-25 and the remaining units will be completed by phases in 2025-26 and 2026-27, so as to shorten the waiting time of public housing.