The Transitional Housing Development is to support the Government policy in providing urgent temporary accommodation, meeting immediate housing demand for the general public. The site is located in Kam Tin, aiming to provide 1,998 nos. of flats in 8 nos. of 4 storey residential blocks constructed with MiC units, with a total GFA of 57,973 m². The development also contains 2 nos. Amenity Blocks providing various ancillary facilities for the residents. The expected completion date will be the end of 2022.
Related News:
20/10/2021 Pok Oi Hospital
元朗過渡性房屋項目—博愛江夏圍村 現正接受申請 為約6,000基層紓解住屋壓力 建構和諧共融新社區 邁向更好未來 (Chinese only)
28/02/2022 Press Release HKSAR Government
Use of transitional housing as community isolation facilities
23/02/2023 Henderson Land Development Company Limited
Client
Architect
Main Contractor
MiC Supplier
Structural Engineer
Building Services Engineer
Highlight on Current Status
Phase 1 Completed in March 2022; Phase 2 Completed in December 2022
Project Current Status
Completed
No. of MiC Modules
2,048
GFA (m²)
Approx. 55, 000
MiC GFA (m²)
54,661
Total Storeys
4
MiC Storeys
4
Anticipated Construction Cycle of Typical MiC floor ( @ Day cycle)
7 Days
Construction Commencement Date
Mar 2021
Anticipated Date of Completion
Q4 2022
Structure
Hybrid
Module Type | Module System | Width (mm) | Length (mm) | Height (mm) | No. | Remarks |
---|---|---|---|---|---|---|
A |
Steel |
2,800 |
6,442 | 3,000 | 1,064 | 1 - 2 ppl |
B | Steel | 3,135 | 8,223 | 3,000 | 884 | 3 - 4 ppl |
C | Steel | 5,610 | 6,442 | 3,000 | 50 | 5-6 ppl and accessible units |
Total | 1,998 |