Kong Ha Wai Transitional Housing Project

Kong Ha Wai, Kam Tin, Yuen Long
Courtesy of Pok Oi Hospital

The Transitional Housing Development is to support the Government policy in providing urgent temporary accommodation, meeting immediate housing demand for the general public. The site is located in Kam Tin, aiming to provide 1,998 nos. of flats in 8 nos. of 4 storey residential blocks constructed with MiC units, with a total GFA of 57,973 m². The development also contains 2 nos. Amenity Blocks providing various ancillary facilities for the residents. The expected completion date will be the end of 2022.

 

Related News:

20/10/2021  Pok Oi Hospital

元朗過渡性房屋項目—博愛江夏圍村 現正接受申請 為約6,000基層紓解住屋壓力 建構和諧共融新社區 邁向更好未來 (Chinese only)

 

28/02/2022  Press Release HKSAR Government

Use of transitional housing as community isolation facilities

 

23/02/2023 Henderson Land Development Company Limited

元朗過渡性房屋項目「博愛江夏圍村」舉行竣工入伙儀式 (Chinese only)

Courtesy of Pok Oi Hospital

Highlight on Current Status

Phase 1 Completed in March 2022; Phase 2 Completed in December 2022

Project Current Status

Completed

No. of MiC Modules

2,048

GFA (m²)

Approx. 55, 000

MiC GFA (m²)

54,661

Total Storeys

4

MiC Storeys

4

Anticipated Construction Cycle of Typical MiC floor ( @ Day cycle)

7 Days

Construction Commencement Date

Mar 2021

Anticipated Date of Completion

Q4 2022

Structure

Hybrid

Design Consultancy Commencement

Sep 2020

Construction Commencement

Mar 2021

Anticipated Date of Completion

Q3 2022

Module Type  Module System Width (mm) Length (mm) Height (mm) No. Remarks

A

Steel

2,800

6,442 3,000 1,064 1 - 2 ppl
B Steel 3,135 8,223 3,000 884 3 - 4 ppl
C Steel 5,610 6,442 3,000 50 5-6 ppl and accessible units
          Total 1,998

    The information contained in this page has been authorised being uploaded.

     

    Disclaimer

    The CIC does not warrant or guarantee the accuracy and suitability of the information contained in this page in any particular case.  The CIC disclaims all liabilities for any loss or damage to any person arising from or as a consequence of the use of or reliance on any information contained in or omitted from this page

Last Updated: 02.06.2023 15:08:33

Adopting MiC to Build Light Public Housing (LPH) to Expedite Housing Supply

The Policy Address 2022 announced the construction of LPH. The LPH Scheme is led by the Architectural Services Department with the adoption of MiC. The Housing Bureau has selected eight sites in Tuen Mun, Yuen Long, Ma On Shan, Kai Tak, Ngau Tau Kok and Chai Wai, providing around 30,000 LPH units. The construction period takes only one to two years. Each units equipped with self-contained toilet and basic facilities such as water heater and air-con. The first batch of around 2,100 units will be completed in 2024-25 and the remaining units will be completed by phases in 2025-26 and 2026-27, so as to shorten the waiting time of public housing.