Quarantine Camp in Penny’s Bay - Phase 4

Fantasy Road, Penny's Bay

Following the completion of Phase 1A of the Penny's Bay Quarantine Camp, the Civil Engineering and Development Department undertook the design and construction for Phase 4 of the quarantine camp in view of the third wave of COVID-19. Capitalising the previous experience in Phase 1A works, the project team stepped up in the productivity and completed the design, manufacturing and installation of 306 units within 41 days.  

Courtesy of CEDD

Highlights on Current Status

In use

Project Current Status

Completed

No. of MiC Modules

306

CFA (m²)

8,070

MiC CFA (m²)

5,508

Superstructure Storeys

2

MiC Storeys

2

Construction Cycle of Typical MiC Floor (@ Day Cycle)

1 Day

Construction Commencement Date

Late Aug 2020

Completion Date

Mid Nov 2020

Structure

Steel

Construction Commencement Date

Late Aug 2020

Assembly Commencement Date

Mid Sep 2020

Assembly Completion Date

Early Oct 2020

Completion Date

Mid Nov 2020

Type of Module

    Type

    Description

    L (mm)

    W (mm)

    H (mm)

    Weight (Tons) per module

    Qty

    Steel

    Habitable units

    3000

    6000

    3200

    11

    306

    The information contained in this page has been authorised being uploaded.

     

    Disclaimer

    The CIC does not warrant or guarantee the accuracy and suitability of the information contained in this page in any particular case. The CIC disclaims all liabilities for any loss or damage to any person arising from or as a consequence of the use of or reliance on any information contained in or omitted from this page.

Last Updated: 14.01.2021 11:19:17

New Isolation Facilities in Hong Kong

Alleviate demand pressure for isolation by MiC and DfMA

In view of the 5th wave of the COVID-19, new isolation facilities and Pop-up Community Vaccination Centres were built by MiC and DfMA with full speed. Eight Community Isolation Facilities projects from China State Construction International providing over 50,000 isolation beds. Supported by the Central Government, the Lok Ma Chau Loop Hospital for Emergency was completed in April 2022. Meanwhile, two MiC transitional housing projects were used as community isolation facilities, providing more than 2,500 units.

防疫速遞 - 啟德社區隔離設施 (Chinese only)

防疫速遞 - 竹篙灣隔離設施工程 (Chinese only)

HOT TOPIC