Following the completion of Phase 1A of the Penny's Bay Quarantine Camp, the Civil Engineering and Development Department undertook the design and construction for Phase 4 of the quarantine camp in view of the third wave of COVID-19. Capitalising the previous experience in Phase 1A works, the project team stepped up in the productivity and completed the design, manufacturing and installation of 306 units within 41 days.
Architect
Main Contractor
MiC Supplier
Structural Engineer
Building Services Engineer
Courtesy of CEDD
Highlights on Current Status
In use
Project Current Status
Completed
No. of MiC Modules
306
CFA (m²)
8,070
MiC CFA (m²)
5,508
Superstructure Storeys
2
MiC Storeys
2
Construction Cycle of Typical MiC Floor (@ Day Cycle)
1 Day
Construction Commencement Date
Late Aug 2020
Completion Date
Mid Nov 2020
Structure
Steel
Last Updated: 14.01.2021 11:19:17
Adopting MiC to Build Light Public Housing (LPH) to Expedite Housing Supply
HOT TOPIC