Quarantine Camp in Penny’s Bay - Phase 4

Fantasy Road, Penny's Bay

Following the completion of Phase 1A of the Penny's Bay Quarantine Camp, the Civil Engineering and Development Department undertook the design and construction for Phase 4 of the quarantine camp in view of the third wave of COVID-19. Capitalising the previous experience in Phase 1A works, the project team stepped up in the productivity and completed the design, manufacturing and installation of 306 units within 41 days.  

Courtesy of CEDD

Highlights on Current Status

In use

Project Current Status

Completed

No. of MiC Modules

306

CFA (m²)

8,070

MiC CFA (m²)

5,508

Superstructure Storeys

2

MiC Storeys

2

Construction Cycle of Typical MiC Floor (@ Day Cycle)

1 Day

Construction Commencement Date

Late Aug 2020

Completion Date

Mid Nov 2020

Structure

Steel

Construction Commencement Date

Late Aug 2020

Assembly Commencement Date

Mid Sep 2020

Assembly Completion Date

Early Oct 2020

Completion Date

Mid Nov 2020

Type of Module

    Type

    Description

    L (mm)

    W (mm)

    H (mm)

    Weight (Tons) per module

    Qty

    Steel

    Habitable units

    3000

    6000

    3200

    11

    306

    The information contained in this page has been authorised being uploaded.

     

    Disclaimer

    The CIC does not warrant or guarantee the accuracy and suitability of the information contained in this page in any particular case. The CIC disclaims all liabilities for any loss or damage to any person arising from or as a consequence of the use of or reliance on any information contained in or omitted from this page.

Last Updated: 14.01.2021 11:19:17

Transitional Housing Projects

In order to relieve the acute shortage of housing, the HKSAR Government announced the three-year transitional housing target of 15,000 units in January 2020. Up to now, two MiC transitional housing projects were completed, including the Nam Cheong 220 by The Hong Kong Council of Social Service and the Junction of Sung Wong Toi Road and To Kwa Wan Road Project by Lok Sin Tong. United Court by Sheng Kung Hui will be commenced shortly. The largest project in Kong Ha Wai by Pok Oi Hospital was commenced in March 2021. Over 6,000 people will be homed by the end of 2022.

江夏圍過渡性房屋計劃 - 首批示範單位落地元朗 (Chinese only)

10.06.2021 AluHouse

樂善堂社會房屋計劃「樂屋」 - 宋皇臺道及土瓜灣道交界組合屋項目 (Chinese only)

03.06.2021 Lok Sin Tong

江夏圍過渡性房屋項目正式動土 (Chinese only)

10.05.2021 City's Time

HOT TOPIC