Composite Development at Ash Street, Tai Kok Tsui

Nos. 5-13 Ash Street, Tai Kok Tsui, Kowloon
Courtesy of URA

The composite development at Ash Street, Tai Kok Tsui is Urban Renewal Authority’s pilot project of using concrete MiC method, which is expected to be the first private residential development of using MiC in Hong Kong upon its completion in 2023.

The project comprises 69 nos. of residential units in a 23-storey residential tower and 3-storey podium.

 

Related News:

7/9/2021  Urban Renewal Authority

URA and Chun Wo Pioneer in Concrete Modular Integrated Construction to Build Hong Kong’s First Private Residential Project

 

Highlights on Current Status

Main Contractor Awarded

Project Current Status

Foundation Works & Main Contractor Awarded

No. of MiC Modules

161

CFA (m²)

4,696

MiC CFA (m²)

2,015

Superstructure Storeys

26

MiC Storeys

23

Construction Cycle of Typical MiC Floor (@ Day Cycle)

4

Construction Commencement Date

Oct 2020

Anticipated Year of Completion

2023

Structure

Concrete

Design Consultancy Commencement Date

Feb 2020

Foundation Works Commencement Date

Oct 2020

Main Contract Commencement Date

Q3 2021

Manufacture of MiC Modules

Q2 2022 - Q4 2022

Installation of MiC Modules

Q4 2022 - Q2 2023

Anticipated Year of Completion

Q4 2023

Module Type No. Width (mm) Length (mm) Length (mm) Inlcuding Corrider & AC Platform Height (mm) Weight (tonnes) No.
A1                    2,385                    4,450                           5,000                    3,140                         21                         23
A1M                    2,385                    4,450                           5,000                    3,140                         21                         23
A2                    2,385                    4,235                           4,235                    3,140                         19                         23
A3                    2,650                    4,710                           4,710                    3,140                         23                         23
B1                    2,835                    5,450                           5,450                    3,140                         27                         23
B1M                    2,835                    5,450                           5,450                    3,140                         27                         23
B2                    2,835                    4,710                           4,710                    3,140                         19                         23

    The information contained in this page has been authorised being uploaded.

     

    Disclaimer

    The CIC does not warrant or guarantee the accuracy and suitability of the information contained in this page in any particular case. The CIC disclaims all liabilities for any loss or damage to any person arising from or as a consequence of the use of or reliance on any information contained in or omitted from this page.

Last Updated: 03.11.2021 14:38:07

New Isolation Facilities in Hong Kong

Alleviate demand pressure for isolation by MiC and DfMA

In view of the 5th wave of the COVID-19, new isolation facilities and Pop-up Community Vaccination Centres were built by MiC and DfMA with full speed. Eight Community Isolation Facilities projects from China State Construction International providing over 50,000 isolation beds. Supported by the Central Government, the Lok Ma Chau Loop Hospital for Emergency was completed in April 2022. Meanwhile, two MiC transitional housing projects were used as community isolation facilities, providing more than 2,500 units.