Yip Shing Street Modular Social Housing Project

Nos. 5-7 Yip Shing Street, Kwai Chung
Courtesy of HKCSS

Modular Social Housing - Yip Shing Street Modular Social Housing Project adopt modular integrated construction to build transitional social housing in idle land. We aim to provide affordable and transitional social housing to families and persons whom queued for the public rental housing and/ or currently live in dismal and inadequate housing conditions so that their living quality can be improved.


HKCSS is building 1 block with 4-storey modular housing and provide around 100 units.The types of unit inlcuded 1-person household unit, 2-person household unit and  accessible units at ground floor. 

Courtesy of HKCSS

Highlights on Current Status

Completed in December 2022

Project Current Status

Completed

No. of MiC Modules

123

GFA (m²)

2,836

Superstructure Storeys

4

MiC Storeys

4

Construction Cycle of Typical MiC Floor (@ Day cycle)

15

Construction Commencement Date

Q3 2021

Date of Completion

Q4 2022

Structure

Steel

Construction Commencement Date

Q3 2021

Manufacture of MiC Modules

Dec 2021 - Mar 2022

Installation of MiC Modules

Q3 2022 - Q4 2022

Date of Completion

Q4 2022

Module Type 

Module System

Width (mm) Length (mm)  Length (mm) Including Corridor & AC Platform Height (mm) Weight (tonnes) No.
SA1 Steel 2,430 6,690 7,115 3,135 11.44 3
SA1a Steel 2,430 6,690 7,115 3,135 11.44 1
SA2 Steel 2,430 6,690 7,115 3,135 11.29 7
SA2a Steel 2,430 6,690 7,115 3,135 11.29 1
SA2M Steel 2,430 6,690 7,115 3,135 11.29 7
SA2Ma Steel 2,430 6,690 7,115 3,135 11.29 2
SA3 Steel 2,430 6,690 7,115 3,135 11.29 6
SA3a Steel 2,430 6,690 7,115 3,135 11.29 5
SA3M Steel 2,430 6,690 7,115 3,135 11.29 3
SA3Ma Steel 2,430 6,690 7,115 3,135 11.29 3
SA3Mb Steel 2,430 6,690 7,115 3,135 11.29 2
SA4 Steel 2,430 6,690 7,115 3,135 11.26 3
SA4a Steel 2,430 6,690 7,115 3,135 11.26 4
SA5a Steel 2,430 6,690 7,115 3,135 11.43 1
SA5b Steel 2,430 6,690 7,115 3,135 11.43 2
SB1 Steel 2,430 6,690 6,690 3,135 11.23 1
SB2 Steel 2,430 6,690 6,690 3,135 10.62 2
SB3 Steel 2,430 6,690 6,690 3,135 10.62 1
SF1 Steel 2,430 12,200 13,050 3,135 20.56 1
SF2 Steel 2,430 12,200 13,050 3,135 19.71 1
SF2a Steel 2,430 12,200 13,050 3,135 19.71 1
SF3 Steel 2,430 12,200 13,050 3,135 19.71 1
SC2 Steel 2,430 12,200 13,050 3,135 20.63 14
SC2a Steel 2,430 12,200 13,050 3,135 20.63 2
SC2M Steel 2,430 12,200 13,050 3,135 20.63 12
SC2Ma Steel 2,430 12,200 13,050 3,135 20.63 5
SD1 Steel 2,430 12,200 13,050 3,135 20.6 1
SE1 Steel 2,430 12,200 12,200 3,135 21.16 1
SE2 Steel 2,430 12,200 12,200 3,135 19.28 2
SE3 Steel 2,430 12,200 13,100 3,135 19.28 1
DJ1L Steel 2,482 5,490 5,490 574 5.47 1
DJ1R Steel 2,482 5,490 5,490 574 5.47 2
SR01 Steel 150 7,112 7,112 1155 0.87 12
SR02 Steel 150 13,019 13,019 1155 1.69 8
SA2M Steel 2,430 6,690 7,115 3135 6.87 1
SA5b Steel 2,430 6,690 7,115 3135 11.28 1
SA3a Steel 2,430 6,690 7,115 3135 6.87 1
SA4a Steel 2,430 6,690 7,115 3135 6.87 1
Total             123

    The information contained in this page has been authorised being uploaded.

     

    Disclaimer

    The CIC does not warrant or guarantee the accuracy and suitability of the information contained in this page in any particular case. The CIC disclaims all liabilities for any loss or damage to any person arising from or as a consequence of the use of or reliance on any information contained in or omitted from this page.

Last Updated: 08.06.2023 16:43:45

Adopting MiC to Build Light Public Housing (LPH) to Expedite Housing Supply

The Policy Address 2022 announced the construction of LPH. The LPH Scheme is led by the Architectural Services Department with the adoption of MiC. The Housing Bureau has selected eight sites in Tuen Mun, Yuen Long, Ma On Shan, Kai Tak, Ngau Tau Kok and Chai Wai, providing around 30,000 LPH units. The construction period takes only one to two years. Each units equipped with self-contained toilet and basic facilities such as water heater and air-con. The first batch of around 2,100 units will be completed in 2024-25 and the remaining units will be completed by phases in 2025-26 and 2026-27, so as to shorten the waiting time of public housing.