Crowne Plaza Changi Airport

Singapore
Courtesy of Crowne Plaza Changi Airport
  • Main Contractor​: Dragages​
  • Modules Supplier​: Unitised Building​
  • Type of Modules​: Steel
  • Gross Floor Area​: 10,000 m²
  • A 10-storey airport hotel, providing 243 rooms
  • Number of MiC Modules: 252
  • Modules Installation Time: about 26 days
  • Project Construction Period: about 17 months (2014-2016)
  • First hotel project which adopted MiC technology in Singapore

 

Reference: Dragages

Last Updated: 23.12.2020 14:45:21

Quickly build high-quality Light Public Housing with MiC

The Policy Address 2022 announced the construction of Light Public Housing (LPH)

The LPH Scheme will be led by the Architectural Services Department with the adoption of MiC. The Housing Bureau has selected eight sites in Tuen Mun, Yuen Long, Sheung Shui, Kai Tak, Ngau Tau Kok and Chai Wai, providing around 30,000 LPH units. The construction period takes only one to two years. Each units equipped with self-contained toilet and basic facilities such as water heater and air-con. The first batch of around 2,100 units will be completed in 2024-25 and the remaining units will be completed by phases in 2025-26 and 2026-27, so as to shorten the waiting time of public housing.

HOT TOPIC