Residential Project at No. 8, Huabichang Hutong, Beijing

Beijing, China
Courtesy of Zhuhai Media Group Company Limited
  • Main Contractor​ and Modules Supplier: China State Construction Hailong Technology Company Limited
  • Type of Modules​: Concrete
  • Project Period: 2024
  • One block of 5-storey residential building
  • The first concrete MiC project in Beijing
  • Number of MiC Modules: 55
  • Number of Units: 20
  • Project Construction Period: Around 3 months
  • An In-situ redevelopment project for old buildings
  • More than 90% of each modules, including decoration, E&M, water pipes, ventilation system, are completed in the factory
Last Updated: 03.06.2024 15:21:10

Adopting MiC to Build Light Public Housing (LPH) to Expedite Housing Supply

The Policy Address 2022 announced the construction of LPH. The LPH Scheme is led by the Architectural Services Department with the adoption of MiC. The Housing Bureau has selected eight sites in Tuen Mun, Yuen Long, Ma On Shan, Kai Tak, Ngau Tau Kok and Chai Wai, providing around 30,000 LPH units. The construction period takes only one to two years. Each units equipped with self-contained toilet and basic facilities such as water heater and air-con. The first batch of around 2,100 units will be completed in 2024-25 and the remaining units will be completed by phases in 2025-26 and 2026-27, so as to shorten the waiting time of public housing.