Residential Project in Lunghua District

Shenzhen, China
Courtesy of Shenzhen Talent Anju Group Company Limited
  • Main Contractor​: China Overseas Construction Limited
  • Modules Supplier: China State Construction Hailong Technology Company Limited
  • Type of Modules​: Concrete
  • Project Period: Jun 2022 - Jun 2023
  • Five 28-storey residential towers with a height of approx.100m
  • The first 100m high-rise concrete MiC affordable housing project in Mainland China
  • Number of MiC Modules: 6,028
  • Number of Units: 2,740
  • Project Construction Period: Around 1 year
  • The fastest-built high-rise affordable housing project in the Mainland China
  • The first project adopting BIM full life cycle digitalisation in Mainland China
  • More than 90% of each modules, including decoration, E&M, water pipes, ventilation system, are completed in the factory
Last Updated: 19.07.2023 15:54:01

Adopting MiC to Build Light Public Housing (LPH) to Expedite Housing Supply

The Policy Address 2022 announced the construction of LPH. The LPH Scheme is led by the Architectural Services Department with the adoption of MiC. The Housing Bureau has selected eight sites in Tuen Mun, Yuen Long, Ma On Shan, Kai Tak, Ngau Tau Kok and Chai Wai, providing around 30,000 LPH units. The construction period takes only one to two years. Each units equipped with self-contained toilet and basic facilities such as water heater and air-con. The first batch of around 2,100 units will be completed in 2024-25 and the remaining units will be completed by phases in 2025-26 and 2026-27, so as to shorten the waiting time of public housing.

HOT TOPIC