Apex House

Wembley, London, United Kingdom
Courtesy of Vision Modular
  • Main Contractor​: Tide Construction Development​
  • Modules Supplier: Vision Modular Systems​
  • Type of Modules​: Hybrid (Steel + Concrete)​
  • A 29-storey, 81 m high student accommodation with 558 rooms   
  • Tallest MiC building in Europe as of 2017
  • Number of MiC Modules: 679
  • Modules Installation Time: Around 13 weeks
  • Project Construction Period: Around 14 months
  • On-site manpower savings​: Only 22 on-site worker​s

 

Reference: Tide Construction and Vision Modular

Last Updated: 23.12.2020 14:45:21

New Isolation Facilities in Hong Kong

Alleviate demand pressure for isolation by MiC and DfMA

In view of the 5th wave of the COVID-19, new isolation facilities and Pop-up Community Vaccination Centres were built by MiC and DfMA with full speed. Eight Community Isolation Facilities projects from China State Construction International providing over 50,000 isolation beds. Supported by the Central Government, the Lok Ma Chau Loop Hospital for Emergency was completed in April 2022. Meanwhile, two MiC transitional housing projects were used as community isolation facilities, providing more than 2,500 units.

防疫速遞 - 啟德社區隔離設施 (Chinese only)

防疫速遞 - 竹篙灣隔離設施工程 (Chinese only)

HOT TOPIC