Apex House

Wembley, London, United Kingdom
Courtesy of Vision Modular
  • Main Contractor​: Tide Construction Development​
  • Modules Supplier: Vision Modular Systems​
  • Type of Modules​: Hybrid (Steel + Concrete)​
  • A 29-storey, 81 m high student accommodation with 558 rooms   
  • Tallest MiC building in Europe as of 2017
  • Number of MiC Modules: 679
  • Modules Installation Time: Around 13 weeks
  • Project Construction Period: Around 14 months
  • On-site manpower savings​: Only 22 on-site worker​s

 

Reference: Tide Construction and Vision Modular

Last Updated: 23.12.2020 14:45:21

About MiMEP

Multi-trade Integrated Mechanical, Electrical and Plumbing (MiMEP) is the integration of multi-trade building services components, into a single volumetric assembly of prefabricated modules, manufactured off-site in a workshop, then transported to the site for connection of modules to complete various trades of building services installations to minimise on-site works. MiMEP can integrate with structural element, architectural builders’ works and finishes (ABWF) to form an advanced assembly, such as false ceiling unit and plant room unit to enhance the productivity.