Apex House

Wembley, London, United Kingdom
Courtesy of Vision Modular
  • Main Contractor​: Tide Construction Development​
  • Modules Supplier: Vision Modular Systems​
  • Type of Modules​: Hybrid (Steel + Concrete)​
  • A 29-storey, 81 m high student accommodation with 558 rooms   
  • Tallest MiC building in Europe as of 2017
  • Number of MiC Modules: 679
  • Modules Installation Time: Around 13 weeks
  • Project Construction Period: Around 14 months
  • On-site manpower savings​: Only 22 on-site worker​s

 

Reference: Tide Construction and Vision Modular

Last Updated: 23.12.2020 14:45:21

Quickly build high-quality Light Public Housing with MiC

The Policy Address 2022 announced the construction of Light Public Housing (LPH)

The LPH Scheme will be led by the Architectural Services Department with the adoption of MiC. The Housing Bureau has selected eight sites in Tuen Mun, Yuen Long, Sheung Shui, Kai Tak, Ngau Tau Kok and Chai Wai, providing around 30,000 LPH units. The construction period takes only one to two years. Each units equipped with self-contained toilet and basic facilities such as water heater and air-con. The first batch of around 2,100 units will be completed in 2024-25 and the remaining units will be completed by phases in 2025-26 and 2026-27, so as to shorten the waiting time of public housing.

HOT TOPIC