Courtesy of Moderna Homes Pte Ltd
  • Client: KTP International Pte Ltd
  • Modules Supplier: Moderna Homes Pte Ltd
  • Architects: Surbana Jurong Consultants Pte Ltd
  • Main Contractor: Sunray Woodcraft Construction Pte Ltd
  • Type of Modules: Hybrid Steel
  • MiC Area​: 4,466 m²
  • Number of Modules: 182
  • Building Type: COVID-19 Community Care Facility
  • No. of Blocks and Storeys: Proposed Hall 9 CCF at Expo
  • Project Period: Sep 21 - Jan 22

Reference: Moderna Homes Pte Ltd

Last Updated: 14.02.2022 11:32:01

Quickly build high-quality Light Public Housing with MiC

The Policy Address 2022 announced the construction of Light Public Housing (LPH)

The LPH Scheme will be led by the Architectural Services Department with the adoption of MiC. The Housing Bureau has selected eight sites in Tuen Mun, Yuen Long, Sheung Shui, Kai Tak, Ngau Tau Kok and Chai Wai, providing around 30,000 LPH units. The construction period takes only one to two years. Each units equipped with self-contained toilet and basic facilities such as water heater and air-con. The first batch of around 2,100 units will be completed in 2024-25 and the remaining units will be completed by phases in 2025-26 and 2026-27, so as to shorten the waiting time of public housing.