Ibis Style

East Perth, Australia
Courtesy of Pindan Group
  • Main Contractor:  Pindan Group
  • Module Supplier: CIMC Modular Building Systems Holding Co., LTD. (CIMC-MBS)
  • Type of Modules : Steel
  • A 16-storey hotel with 252 rooms
  • Number of Modules: 171
  • Module Installation Time: About 5 months
  • Project Construction Peroid: About 1 year (2018 - 2019) 
  • World’s largest modular hotel; CIMC-MBS designed and installed the curtain wall system which was 100% factory pre-finished

 

Reference: Pindan Group

Last Updated: 12.04.2021 17:24:56

HKICC and Quarantine Camps

To fight COVID-19, the HKSAR Government has built the North Lantau Hospital Hong Kong Infection Control Centre (HKICC) next to the AsiaWorld-Expo providing 136 negative pressure wards which were designed with reference to the standards of tier-1 isolation wards that could accommodate 816 beds. The HKICC adopted MiC method and was completed in merely 4 months (Sep 2020 – Jan 2021). It will open on 26 February 2021.

From blueprint to scale

05.03.2021 Hospital Authority

Infection control centre to open

25.02.2021 HKSAR Government

Temporary hospital completed

20.01.2021 HKSAR Government

Penny's Bay Quarantine Camp Phase 4

07.01.2021 AluHouse

同心抗疫: 鯉魚門檢疫單位投入運作 (Chinese only)

03.03.2020 Information Services Centre

HOT TOPIC