Shanghai 6th People's Hospital - Isolation Ward

600 Yishan Road, Xuhui District, Shanghai
Shanghai Jiao Tong University School of Medicine
  • Main Contractor: Shanghai Construction Group Company Limited 
  • Module Supplier: Zhejiang Jiutai Integrated Housing Tech. Co., Ltd.
  • No. of Storey: 2
  • Construction Area: 663 m²
  • Number of Modules: 28
  • Construction Period: 20 Days
  • Project Completion Date: Feb 2020
  • Facilities: The 10 wards include 14 isolation beds equipped with a dedicated CT room and DR room, each ward equipped with split air conditioners, independent toilets and independent shower rooms, and dual-channel branches for medical passages and patient passages

 

Reference: Mmoon Prefab House

Last Updated: 08.04.2021 10:11:08

2021 Policy Address

2021 Policy Address and MiC

The Chief Executive issues the 2021 Policy Address on October 7, 2021. It mentions the government will continue to implement “Construction 2.0” so as to uplift the productivity and skill level of the sector. Wider use of I&T and Modular Integrated Construction (MiC) will also be promoted to shorten construction time, reduce manpower and enhance safety in construction sites. Moreover, in order to increase and speed up the housing supply, the HKHA and the Hong Kong Housing Society (HKHS) will adopt the MiC and other innovative construction technology more widely. The HKHA will also adopt a new procurement model to suitable projects to allow contractors to undertake design and construction in a bundle. It is hoped that these measures can further optimise and speed up the construction process.