Futian MiC Schools

Shenzhen, Mainland China
Courtesy of CIMC-MBS
  • Client: Futian District Government
  • Modules Supplier: CIMC Modular Building Systems Holding Co., LTD. (CIMC-MBS)
  • Type of Modules: Steel
  • Gross Floor Area​: 38,000 m²
  • Number of Floors: 5 blocks of school with 2-3 floors
  • Number of Classrooms: 140
  • Number of Modules: 585
  • Project Period: 180 days (1/3/2020 - 21/8/2020)
  • Modules Installation Time: 55-70 days for each block
  • MiC Part: Each classroom is composed of 2 MiC modules

Reference: CIMC-MBS

Design Commencement Date

1 Mar 2020

Modules Manufacturing Commencement Date

1 Jun 2020

Modules Manufacturing Completion Date

10 Jul 2020

Modules Installation Commencement Date

1 Aug 2020

Completion Date

21 Aug 2020

Last Updated: 27.01.2021 11:02:09

Quickly build high-quality Light Public Housing with MiC

The Policy Address 2022 announced the construction of Light Public Housing (LPH)

The LPH Scheme will be led by the Architectural Services Department with the adoption of MiC. The Housing Bureau has selected eight sites in Tuen Mun, Yuen Long, Sheung Shui, Kai Tak, Ngau Tau Kok and Chai Wai, providing around 30,000 LPH units. The construction period takes only one to two years. Each units equipped with self-contained toilet and basic facilities such as water heater and air-con. The first batch of around 2,100 units will be completed in 2024-25 and the remaining units will be completed by phases in 2025-26 and 2026-27, so as to shorten the waiting time of public housing.

HOT TOPIC