Futian MiC Schools

Shenzhen, Mainland China
Courtesy of CIMC-MBS
  • Client: Futian District Government
  • Modules Supplier: CIMC Modular Building Systems Holding Co., LTD. (CIMC-MBS)
  • Type of Modules: Steel
  • Gross Floor Area​: 38,000 m²
  • Number of Floors: 5 blocks of school with 2-3 floors
  • Number of Classrooms: 140
  • Number of Modules: 585
  • Project Period: 180 days (1/3/2020 - 21/8/2020)
  • Modules Installation Time: 55-70 days for each block
  • MiC Part: Each classroom is composed of 2 MiC modules

Reference: CIMC-MBS

Design Commencement Date

1 Mar 2020

Modules Manufacturing Commencement Date

1 Jun 2020

Modules Manufacturing Completion Date

10 Jul 2020

Modules Installation Commencement Date

1 Aug 2020

Completion Date

21 Aug 2020

Last Updated: 27.01.2021 11:02:09

HKICC and Quarantine Camps

To fight COVID-19, the HKSAR Government has built the North Lantau Hospital Hong Kong Infection Control Centre (HKICC) next to the AsiaWorld-Expo providing 136 negative pressure wards which were designed with reference to the standards of tier-1 isolation wards that could accommodate 816 beds. The HKICC adopted MiC method and was completed in merely 4 months (Sep 2020 – Jan 2021). It will open on 26 February 2021.

From blueprint to scale

05.03.2021 Hospital Authority

Infection control centre to open

25.02.2021 HKSAR Government

Temporary hospital completed

20.01.2021 HKSAR Government

Penny's Bay Quarantine Camp Phase 4

07.01.2021 AluHouse

同心抗疫: 鯉魚門檢疫單位投入運作 (Chinese only)

03.03.2020 Information Services Centre

HOT TOPIC