Futian MiC Schools

Shenzhen, Mainland China
Courtesy of CIMC-MBS
  • Client: Futian District Government
  • Modules Supplier: CIMC Modular Building Systems Holding Co., LTD. (CIMC-MBS)
  • Type of Modules: Steel
  • Gross Floor Area​: 38,000 m²
  • Number of Floors: 5 blocks of school with 2-3 floors
  • Number of Classrooms: 140
  • Number of Modules: 585
  • Project Period: 180 days (1/3/2020 - 21/8/2020)
  • Modules Installation Time: 55-70 days for each block
  • MiC Part: Each classroom is composed of 2 MiC modules

Reference: CIMC-MBS

Design Commencement Date

1 Mar 2020

Modules Manufacturing Commencement Date

1 Jun 2020

Modules Manufacturing Completion Date

10 Jul 2020

Modules Installation Commencement Date

1 Aug 2020

Completion Date

21 Aug 2020

Last Updated: 27.01.2021 11:02:09

2021 Policy Address

2021 Policy Address and MiC

The Chief Executive issues the 2021 Policy Address on October 7, 2021. It mentions the government will continue to implement “Construction 2.0” so as to uplift the productivity and skill level of the sector. Wider use of I&T and Modular Integrated Construction (MiC) will also be promoted to shorten construction time, reduce manpower and enhance safety in construction sites. Moreover, in order to increase and speed up the housing supply, the HKHA and the Hong Kong Housing Society (HKHS) will adopt the MiC and other innovative construction technology more widely. The HKHA will also adopt a new procurement model to suitable projects to allow contractors to undertake design and construction in a bundle. It is hoped that these measures can further optimise and speed up the construction process.