Xiong’an Citizen Service Center Corporate Office Area

Hebei, China
Courtesy of Sohu
  • Modules Supplier​: CIMC
  • Type of Modules: Steel 
  • Gross Floor Area: 30,000 m²
  • A state-level new area (formed on 1 April 2017) located approximately 100 km southwest of Beijing
  • Management Office composed of 5 office buildings and 1 hotel
  • Number of MiC Modules: 593
  • Project Construction Period: Around 90 days 

 

Reference: CIMC

Last Updated: 23.12.2020 14:45:21

HKICC and Quarantine Camps

To fight COVID-19, the HKSAR Government has built the North Lantau Hospital Hong Kong Infection Control Centre (HKICC) next to the AsiaWorld-Expo providing 136 negative pressure wards which were designed with reference to the standards of tier-1 isolation wards that could accommodate 816 beds. The HKICC adopted MiC method and was completed in merely 4 months (Sep 2020 – Jan 2021). It will open on 26 February 2021.

From blueprint to scale

05.03.2021 Hospital Authority

Infection control centre to open

25.02.2021 HKSAR Government

Temporary hospital completed

20.01.2021 HKSAR Government

Penny's Bay Quarantine Camp Phase 4

07.01.2021 AluHouse

同心抗疫: 鯉魚門檢疫單位投入運作 (Chinese only)

03.03.2020 Information Services Centre

HOT TOPIC