Ten Degrees Croydon

Croydon, London, United Kingdom
Courtesy of HTA Design
  • Main Contractor : Tide Construction Development
  • Module Supplier : Vision Modular Systems
  • Type of Modules : Steel
  • Gross Floor Area: 41,819 m²
  • 2 towers with 44 and 38 storeys respectively and comprise 546 residential units
  • Number of Modules: 1500
  • Construction Period: 2018 - 2021 (39 months)
  • The tallest steel MiC building in the world now

 

Reference: HTA Design

Last Updated: 15.06.2021 09:26:27

Adopting MiC to Build Light Public Housing (LPH) to Expedite Housing Supply

The Policy Address 2022 announced the construction of LPH. The LPH Scheme is led by the Architectural Services Department with the adoption of MiC. The Housing Bureau has selected eight sites in Tuen Mun, Yuen Long, Ma On Shan, Kai Tak, Ngau Tau Kok and Chai Wai, providing around 30,000 LPH units. The construction period takes only one to two years. Each units equipped with self-contained toilet and basic facilities such as water heater and air-con. The first batch of around 2,100 units will be completed in 2024-25 and the remaining units will be completed by phases in 2025-26 and 2026-27, so as to shorten the waiting time of public housing.

HOT TOPIC