Ten Degrees Croydon

Croydon, London, United Kingdom
Courtesy of HTA Design
  • Main Contractor : Tide Construction Development
  • Module Supplier : Vision Modular Systems
  • Type of Modules : Steel
  • Gross Floor Area: 41,819 m²
  • 2 towers with 44 and 38 storeys respectively and comprise 546 residential units
  • Number of Modules: 1500
  • Construction Period: 2018 - 2021 (39 months)
  • The tallest steel MiC building in the world now

 

Reference: HTA Design

Last Updated: 15.06.2021 09:26:27

Transitional Housing Projects

In order to relieve the acute shortage of housing, the HKSAR Government announced the three-year transitional housing target of 15,000 units in January 2020. Up to now, two MiC transitional housing projects were completed, including the Nam Cheong 220 by The Hong Kong Council of Social Service and the Junction of Sung Wong Toi Road and To Kwa Wan Road Project by Lok Sin Tong. United Court by Sheng Kung Hui will be commenced shortly. The largest project in Kong Ha Wai by Pok Oi Hospital was commenced in March 2021. Over 6,000 people will be homed by the end of 2022.

江夏圍過渡性房屋計劃 - 首批示範單位落地元朗 (Chinese only)

10.06.2021 AluHouse

樂善堂社會房屋計劃「樂屋」 - 宋皇臺道及土瓜灣道交界組合屋項目 (Chinese only)

03.06.2021 Lok Sin Tong

江夏圍過渡性房屋項目正式動土 (Chinese only)

10.05.2021 City's Time

HOT TOPIC