As the first EMSD pilot project completed using the MiMEP method, the two-phase rooftop project involved replacing three chillers and an independent chilled water pump module while ensuring uninterrupted air conditioning.
With over 80% modularization, construction time was reduced from 90 to 38 days, greatly minimizing client impact. Post-completion, BIM linked with BIM-AM system and RFID technology enables smart maintenance management.
Related News:
16/12/2025 Electrical and Mechanical Services Department
The EMSD’s First Adoption of MiMEP and BIM Technology for Chiller System Replacement
Maintenance Agency
E&M Contractor
Highlights on Current Status
In-use
Project Current Status
Completed
No. of MiMEP Modules
8
CFA (m²)
110
MiMEP CFA (m²)
75
Superstructure Storeys
1
MiMEP Storeys
1
MiMEP Area to CFA in Typical floors (%)
68
Project Commencement
Sep 2021
Project Completion
Apr 2022
MiMEP Coverage (%)
80
| Module Type | Description | W (mm) | L (mm) | H (mm) | Weight (kg) | Qty |
|---|---|---|---|---|---|---|
|
Chiller System |
Chilled Water Pipe Header |
1550 |
3000 |
300 |
480 |
1 |
|
Chiller System |
Chilled Water Pipe Header |
1550 |
3500 |
300 |
520 |
1 |
|
Chiller System |
Chilled Water Pipe Header |
1550 |
3300 |
300 |
500 |
1 |
|
Chiller System |
Chilled Water Pipe Header |
1550 |
3100 |
300 |
490 |
1 |
|
Chiller System |
Chilled Water Valve Set |
65 |
3000 |
165 |
200 |
1 |
|
Chiller System |
Chilled Water Valve Set |
65 |
5400 |
165 |
360 |
1 |
|
Chiller System |
Chilled Water Valve Set |
65 |
4500 |
165 |
300 |
1 |
|
Modular |
Modular Pump Set with Control Panel |
2050 |
4250 |
3100 |
2798 |
1 |
|
|
|
|
|
|
Total |
8 |
About MiMEP