Transitional Housing Project at Area 1B3, Muk On Street, Kai Tak

Muk On Street, Kai Tak

The project is the 2nd transitional Housing project of Food for Good Limited. Four-storey building provides approximately 700 units. Each unit will be equipped with a bathroom with toilet and a cooking area. it is targeted to completed in Q4 2023. 

Highlights on Current Status

Module Fabrication

Project Current Status

Under Construction

No. of MiC Modules

774

GFA (m²)

15,952

MiC GFA (m²)

14,465

Total Storeys

4

MiC Storeys

4

Construction Cycle of Typical MiC Floor (@ Day Cycle)

TBA

Construction Commencement Date

Q4 2022

Anticipated Date of Completion

Q4 2023

Structure

Steel

Construction Commencement

Q4 2022

Module Installation

June - Aug 2023

Date of Completion

Q4 2023

    The information contained in this page has been authorised being uploaded.

     

    Disclaimer

    The CIC does not warrant or guarantee the accuracy and suitability of the information contained in this page in any particular case. The CIC disclaims all liabilities for any loss or damage to any person arising from or as a consequence of the use of or reliance on any information contained in or omitted from this page.

Last Updated: 14.07.2023 16:18:39

Quickly build high-quality Light Public Housing with MiC

The Policy Address 2022 announced the construction of Light Public Housing (LPH)

The LPH Scheme will be led by the Architectural Services Department with the adoption of MiC. The Housing Bureau has selected eight sites in Tuen Mun, Yuen Long, Ma On Shan, Kai Tak, Ngau Tau Kok and Chai Wai, providing around 30,000 LPH units. The construction period takes only one to two years. Each units equipped with self-contained toilet and basic facilities such as water heater and air-con. The first batch of around 2,100 units will be completed in 2024-25 and the remaining units will be completed by phases in 2025-26 and 2026-27, so as to shorten the waiting time of public housing.

HOT TOPIC