Nam Cheong 220

202 - 220 Nam Cheong Street, Sham Shui Po
Courtesy of HKCSS

Modular Social Housing Projects adopt modular integrated construction to build transitional social housing in idle land. HKCSS aims to provide affordable and transitional social housing to families and persons whom queued for the public rental housing and/ or currently live in dismal and inadequate housing conditions so that their living quality can be improved.

Expected to provide totally 89 units. The internal floor area of each unit is between around 10 sqm to 25 sqm. Different module size will be provided for 1-person household unit, 2-person household unit, 3-person household unit and accessible unit.

Project timelapse Courtesy of HKCSS

Highlights on Current Status

Tenants Moved In

Project Current Status

Completed

No. of MiC Modules

68

CFA (m²)

2,052

MiC CFA (m²)

2,052

Superstructure Storeys

4

MiC Storeys

4

Construction Cycle of Typical MiC floor ( @ Day cycle)

4 Days

Construction Commencement Date

Aug 2019

Year of Completion

Jul 2020

Structure

Steel

Public Announcement Date on Use of MiC

Jun 2018

Construction Commencement Date

Aug 2019

Modules Manufacturing Commencement Date

Nov 2019

Assembly Commencement Date

Dec 2019

Year of Completion

Jul 2020

Tenant Move in

Aug 2020

Learn more about the project

Watch the interview with the Client and the Members of the Project Team of "Nam Cheong 220"

PLAYLIST

    The information contained in this page has been authorised being uploaded.

     

    Disclaimer

    The CIC does not warrant or guarantee the accuracy and suitability of the information contained in this page in any particular case.  The CIC disclaims all liabilities for any loss or damage to any person arising from or as a consequence of the use of or reliance on any information contained in or omitted from this page.

Last Updated: 03.03.2021 17:40:01

HKICC and Quarantine Camps

To fight COVID-19, the HKSAR Government has built the North Lantau Hospital Hong Kong Infection Control Centre (HKICC) next to the AsiaWorld-Expo providing 136 negative pressure wards which were designed with reference to the standards of tier-1 isolation wards that could accommodate about 820 beds. The HKICC adopted MiC method and was completed in merely 4 months (Sep 2020 – Jan 2021). It will open on 26 February 2021.

From blueprint to scale

05.03.2021 Hospital Authority

Infection control centre to open

25.02.2021 HKSAR Government

Temporary hospital completed

20.01.2021 HKSAR Government

Penny's Bay Quarantine Camp Phase 4

07.01.2021 AluHouse

同心抗疫: 鯉魚門檢疫單位投入運作 (Chinese only)

03.03.2020 Information Services Centre

HOT TOPIC